Timelines · and how to compress them

What actually takes long in a Dutch renovation

Almost nobody underestimates how long building takes. Almost everybody underestimates how long everything before the building takes.

Loft stripped back to the roof structure during a renovation, ready for insulation

Question about your own house?

Send a photo or a short description on WhatsApp. You usually get an answer the same working day.

Ask us on WhatsApp
Why international owners work with us

A Rotterdam contractor that works in English

We are a family business based in Rotterdam. A growing share of our clients moved here from elsewhere, which is why we set the process up to work without you having to navigate the Dutch system yourself.

English throughout

One point of contact who works in English, with written summaries of every decision so nothing depends on a conversation.

Our own team

20 to 30 tradespeople on our own payroll rather than subcontractors, so coordination between trades is our problem and not yours.

We handle the paperwork

Structural engineer, permit application and the owners' association request, started in parallel so they stay off your critical path.

Assessment before you buy

We look at feasibility as well as condition, at the point where the information can still change your decision.

One clear price

A specified quotation with labour and materials separated, exclusions stated and payment tied to progress rather than to dates.

A one-year guarantee

On the renovation work we carry out, alongside the manufacturer warranties on the products we install.

In short
  • Preparation runs in months; construction runs in weeks.
  • The four long poles are: structural calculation, permit, owners' association and material lead times.
  • Anything that can run in parallel should.
  • Late decisions are the most common cause of delay, and the easiest to avoid.
  • Drying times are not compressible; plan around them rather than against them.

"When can you start?" is the wrong first question. The right one is "what has to be settled before anyone can start, and how long does each of those take?" This guide answers that, phase by phase, and sets out what genuinely shortens a project.

The shape of a project

PhaseTypical durationCan it run in parallel?
Survey and initial adviceDays to weeks
Archive drawingsDays to weeksYes, start immediately
Design and layout decisionsWeeksPartly
Structural calculationWeeksAfter the openings are fixed
Owners' association consentWeeks to monthsYes — start first
Permit applicationEight weeks, extendableYes, alongside the association
Material selection and orderingWeeks to monthsYes, throughout
Demolition and strip-outDays to weeks
Structural workDays to weeks
First fix servicesWeeks
Closing up, screed, plasterWeeks, plus drying
Finishes and second fixWeeks
Handover and snaggingDays to weeks

Everything in the top half can overlap. Almost nothing in the bottom half can. That is why the front end deserves the attention.

The four long poles

  1. The owners' association. If you are in an apartment, this is usually the longest single wait, because decisions are taken at meetings that may be annual. Start it before anything else.
  2. The permit. A regular procedure runs eight weeks and can be extended by six, followed by a six-week objection period. An incomplete application costs a full round.
  3. The structural calculation. Weeks, and it cannot begin until the opening dimensions are final. Changing them afterwards means starting again.
  4. Material lead times. Kitchens, made-to-measure joinery, window frames and some tiles and stone run to weeks or months. This is the one people forget, and it is entirely predictable.
The compression rule

You cannot make any of these four faster. You can only start them earlier and run them at the same time. That is the whole of timeline management on a renovation.

Decisions are the hidden critical path

The most common cause of delay is not a slow trade or a slow municipality. It is a decision that has not been made.

The fix is to schedule the decisions rather than the tasks. Every choice has a latest date, derived from the lead time and the sequence:

DecisionNeeded byWhy
Layout and which walls moveBefore anythingDrives demolition, structure and services
Opening dimensionsBefore the calculationChanging them restarts the engineering
Socket, switch and lighting positionsBefore first fixAfterwards means chasing walls again
Sanitary ware and tapsBefore plumbing first fixDetermines connection points and heights
KitchenVery earlyLongest lead time; drives services
Floor build-upBefore screedDetermines height, thresholds and doors
TilesWeeks before tilingLead time and quantity
Paint coloursBefore decoratingShortest lead time; least pressure

Ask your contractor for this list with dates at the start. It takes them an hour and it removes most of the stress from the project.

What cannot be compressed

  • Drying times. Screed and plaster need to dry before what follows. Forcing it produces cracking, poor adhesion and callbacks. This is physics, not scheduling.
  • Statutory periods. The permit procedure and the objection period run for their stated duration.
  • Meeting dates. An association meets when it meets.
  • Manufacturing. A made-to-measure kitchen takes as long as it takes.
  • Sequence. Services go in before walls close; walls close before finishes. Overlapping these produces rework.

A contractor who promises to compress any of these is either not planning to do them properly or has not thought it through. Both are worth knowing before you sign.

What genuinely shortens a project

  1. Start the slow items first, in this order: owners' association, archive drawings, structural calculation, permit, long-lead materials.
  2. Fix the design before the calculation. Every subsequent change is expensive in time.
  3. Submit a complete permit application in one go.
  4. Order long-lead items early, even if they will sit in storage.
  5. Make decisions against the schedule, using the decision list with dates.
  6. Use one contractor for the whole scope, so nobody is waiting on someone they do not control.
  7. Empty the property properly before the start. Sounds trivial; costs days when it is not done.

Living in the property during the work

Possible for a limited scope, difficult for a full renovation. Realistically:

  • Single-room work — a bathroom or a kitchen — is manageable, with a period without that room.
  • Structural work means dust, noise and propping, often across several rooms at once. Living in is unpleasant and slows the work.
  • A full renovation with services replaced means periods without power or water. Plan to move out.

Staying in a property under renovation also lengthens the programme, because work has to be phased around your occupation and cleaned down daily. If the decision is finely balanced, moving out is usually faster and cheaper than it looks.

Summary

In a Dutch renovation, preparation runs in months and construction runs in weeks. The four long poles are the owners' association, the permit, the structural calculation and material lead times, and none of them can be made faster — only started earlier and run in parallel. The hidden critical path is decisions, so ask for a list of choices with latest dates at the outset. And accept the things that genuinely cannot be compressed: drying times, statutory periods and manufacturing.

Next: permits or working with a contractor.

Want a realistic programme before you commit?

We set out the phases, the decision dates and the long-lead items at the start, so you know what determines your start date and what determines your finish.

FAQ

Frequently asked questions about renovation timelines

How long does a full renovation take in the Netherlands?
The building work usually runs in weeks; the whole project runs in months. What determines the total is the preparation: owners' association consent, the permit procedure, the structural calculation and material lead times, all of which sit before anyone starts on site.
What is the single longest wait?
In an apartment, the owners' association, because decisions are taken at meetings that may be held annually. In a house, usually the permit procedure or the lead time on a made-to-measure kitchen or window frames.
Can the permit procedure be shortened?
Not the statutory period itself. What you can control is completeness: an incomplete application costs a full assessment round. Submit everything in one go, and run the application in parallel with the association's process rather than after it.
Why do late decisions cause so much delay?
Because they sit on the critical path without appearing on it. A tile chosen two weeks late delays tiling, which delays second fix, which delays handover. Ask your contractor for a list of decisions with latest dates at the start of the project.
Are drying times really unavoidable?
Yes. Screed and plaster have to dry before what follows, and forcing the sequence produces cracking, poor adhesion and callbacks. It is a material property, not a scheduling preference. Plan around it.
What should I order first?
Whatever has the longest lead time, typically the kitchen, made-to-measure joinery and window frames. Order them early even if they will be stored, because they otherwise dictate your finish date regardless of how quickly the building work goes.
Can I live in the house during the renovation?
For single-room work, usually yes. For structural work or a full renovation with services replaced, it is difficult and it lengthens the programme, because work must be phased around you and cleaned down daily. Moving out is often faster and cheaper than it looks.
What happens if the project overruns?
The contract should state the period and how delay is handled. In practice most overruns trace back to late decisions or late material selection rather than to slow building, which is why fixing choices before the start matters so much.
Should I start the VvE process or the permit first?
Both at once, but if you can only start one, start the association. It is the slower of the two and the one you have least control over. The permit application can follow within days once the calculation exists.
How early should I involve a contractor?
Earlier than most people do — ideally before purchase if you are buying. Early involvement is what allows the long items to be started in parallel, and it is the only point at which a survey can still affect your decision.
Free quote

Planning this work on your own house?

Tell us briefly about your home and what you are planning. You get a free quote, usually within one working day.

  • A fixed price up front, no extra costs afterwards
  • Carried out by our own team, no subcontractors
  • One year of guarantee on the work

We usually reply within one working day. No spam, no obligation.